Timeline

County Square Redevelopment Project Updates

  • Spring 2023Current Updates

    • Phase II of demolition will begin in June 2023
    • New County office building exterior is complete. Move in for County Administrative functions anticipated Q2 of 2023
    • In addition to Multi-Family, KDS Caine has been chosen for Hospitality component of project as well
    • First 3 Multi-Family offerings anticipated Q3 of 2023
  • Spring 2022Nearing Completion

    • New County office building exterior is nearing completion. Move in for county administrative functions anticipated in Q1 of 2023.
    • Initial phase of demolition has begun on former family court, health department, and DMV buildings.
    • KDS Caine chosen as broker for Multi-Family component of project.
    • First three Multi-Family offerings anticipated Q2 of 2022.
    • Four additional Multi-Family sites will be available in later phases
  • Summer 2021Site activity

  • Spring 2021Development updates

    • State Agencies to move from County Square to Halton Road Property
    • Family Court Building to be demolished and make way for 1000-car parking garage.
    • Health Department Building and 300 University Ridge building to be demolished.
    • The Foster and Partners designed new Greenville County office will be complete in approximately 18 months and the building will be occupied in Q1 2023.
    • DMV moved to their new home.
  • 2020Demolition and construction began

    • City approved the zoning modification of the existing planned development.
    • Environmental Remediation Process completed.
    • Construction on County Building commenced.
  • 2019Initial plans finalized

    • Met with Urban Design Associates to discuss the City’s South Downtown Master Plan
    • Represented County in acquisition of 230,000sf of Office Space on Halton Road for relocation of state agencies.
    • Cooper Robertson finished the initial land plan.
    • Preliminary site plans were made available during Q2 of 2019.
  • 2018Project development team formed and agreements signed

    • All partners signed their development agreements.
    • Developers RocaPoint Partners/The Georgetown Company, architects Foster+Partners and Wakefield Beasley & Associates, and KDS Caine Commercial Real Estate chosen as the Development Team.